Avenue 50 Bridge in Coachella: What Changes During Construction

October 15, 2026

Coachella's Avenue 50 bridge has a groundbreaking set for October 15, 2026, from 9 a.m. to noon, according to the City of Coachella's event calendar. The project replaces the low-water crossing where Avenue 50 dips down into the Coachella Valley Stormwater Channel. When the channel runs high, that stretch of road can't be used.

The bridge is meant to help drivers, but they won't feel the change for a while. The road dip is expected to stay open through most of construction, and so will its weak spot in storms. CV Link at Avenue 50 closes now and stays closed until the work is finished. That makes the trail, not the road, the first place the project shows up in daily routines.

The Dip Stays Open, and So Does Its Weak Spot

The new bridge sits on a shifted alignment, set off from the current roadway. The Greater Palm Springs Business Insider reported on September 24 that, because of this, the existing low-water crossing "is expected to remain available through much of that period." The outlet said this would limit "what otherwise could have been a major disruption to local traffic." That is a planning expectation, and the same report says city officials expect bridge construction to take roughly two years.

For two more years, then, Avenue 50 works the way it always has. It's a direct route across the channel in dry weather and a closed one when the channel floods. The city has dealt with this for a long time. A 2014 safety background report prepared for Coachella's General Plan update described Avenue 50 as the only crossing of the stormwater channel that dips into it rather than bridging over it, and said the crossing becomes impassable when the channel floods.

The 2023 storm season showed what that means. During Tropical Storm Hilary, The Desert Sun's live updates listed Avenue 50 at the Whitewater Wash among Coachella road closures as of 6 p.m. on August 20, 2023. Less than two weeks later, a KESQ cleanup report dated September 2, 2023, still listed Avenue 50 at the Whitewater Channel among the street closures that remained after heavy rain. Neither report gives a reopening date, so how long the road stayed closed is not on record.

The Trail Closes for the Whole Build

The CV Link side of the project has a firmer schedule. The CV Link construction updates page says "CV Link at Avenue 50 will be closed for the duration of the project," and that a detour will be posted around the construction zone.

That page was last updated in June. It projected an August 2026 start and completion in 2028. The construction contract wasn't awarded until September 21, so both dates are best read as targets. The contract allows 550 working days for the full scope, counted from the notice to proceed. That fits the roughly two-year estimate city officials have given.

According to CVAG's CV Link site, the East Valley segment runs 16.02 miles, from Washington Street in La Quinta to Airport Boulevard in Coachella. The Avenue 50 closure falls on the Coachella end of that stretch. Anyone who rides, runs, or uses a low-speed electric vehicle through this section will be on a posted detour through 2028 or so. Drivers in the same spot will still have the road they know.

The trail comes back changed. In Phase 1, CV Link moves beneath the new bridge and that portion of the path gets rebuilt through the project area. Once it's done, trail users go under traffic at Avenue 50.

When the Channel Runs Before 2028

The low-water crossing will still be in use for most of the next two storm seasons. That makes the other channel crossings worth knowing. The 2014 city report lists three besides Avenue 50:

  1. Dillon Road
  2. Avenue 52
  3. Airport Boulevard, also known as Avenue 56

The report describes these as places where roads cross the channel. It is not an official detour plan, and none of the current coverage of the bridge project includes a published storm detour or a schedule of lane closures for Avenue 50 and Tyler Street during construction. The City of Coachella and local news outlets will put out those notices if and when the work requires them.

Why a Bridge Funded in 2014 Is Breaking Ground in 2026

This project has been underway for a long time. KESQ's September 23 report traced the timeline. The city first received federal bridge funding authorization in 2014 and finished environmental review in 2019. Right-of-way acquisition and design were then slowed by eminent domain proceedings, coordination with tribal and regional entities, and the COVID-19 pandemic.

Milestone Date
Federal bridge funding authorized 2014
Environmental review completed 2019
Notice inviting bids issued July 9, 2026
Mandatory job walk July 28, 2026
Bids opened, seven received September 3, 2026
Contract awarded to Riverside Construction Company September 21, 2026
Groundbreaking scheduled October 15, 2026
Projected completion, per CV Link 2028

After all those delays, the bid came in low. The City Council awarded Riverside Construction Company a contract for $48,709,821.10, which includes a 10% contingency of $4,870,982.10. KESQ reported that this was about $7 million under the city's original budget estimate. With $7.9 million in construction management fees added, the total project cost is $61,551,444.

The funding also explains why the project could go ahead without touching the city's general fund. KESQ broke down the sources this way:

  • About $49 million in state bridge funds through the Highway Bridge Program
  • Nearly $9.5 million from the Coachella Valley Association of Governments
  • $1.6 million from Measure A
  • $1.73 million from Senate Bill 1 revenue
  • Local water funds

The Measure A and SB 1 money was set aside on purpose over several years to protect general fund reserves, according to the same report. At the September 21 meeting, Mayor Dr. Frank Figueroa called the project "a big win for the city of Coachella," KESQ reported, and added, "I can't wait to do the groundbreaking."

What Opens on the Other Side of Phase 1

When the bridge opens, the corridor will look different. The design calls for a five-span bridge, roadway improvements on Avenue 50 and Tyler Street, a new traffic signal, and utility work. Tyler Street gets realigned, and the new road temporarily connects to the existing signal at Highway 86. A later phase would build a full interchange at Highway 86 and Avenue 50. The Highway 86 connection you'll use in 2028 is a temporary arrangement, and more construction is planned after it.

The Business Insider pointed to growth as the reason the corridor carries more weight now. It noted that Avenue 50 serves areas where residential development is expanding and where more commercial and industrial activity is planned or underway. More trail work is coming nearby too. The CV Link site says construction on the Arts and Music Line, a community connector along Avenue 48 and Dillon Road through La Quinta, Indio and Coachella, is expected to begin in 2027. That timing would put two separate CV Link projects under construction in this part of the valley at once.

Until then, Coachella's fall calendar goes on unaffected, since its venues are downtown and away from the construction. The free Tacos, Tequila, & Chavelas Festival runs Saturday, October 17, from 4 to 8 p.m. at Veterans' Memorial Park, 1515 Sixth Street, two days after the groundbreaking. The 13th Annual Run with Los Muertos 5K and block party takes over Old Town Coachella on November 7. The pre-race ceremony starts at 4 p.m., the race at 6 p.m., and art and music run until midnight, according to the race registration page. Registration prices go up after October 26.

If you own a home near the Avenue 50 corridor, or are thinking about one east of the channel, Charles Gallagher keeps track of projects like this one across the Coachella Valley and can walk you through what the construction schedule means for access, timing, and how a property presents while the work is underway. Let's Connect.